Why the refund guarantee is the centre of the deal

Newbuild payments are instalments tied to construction milestones, so an owner typically pays 30–60% of the price before delivery. If the yard fails to deliver — insolvency, major delay, or termination — that money is at risk. A refund guarantee issued by a bank obliges the bank to repay the pre-delivery instalments if the yard does not perform.

Who issues it

  • Chinese banks: the yard's bank issues the guarantee, ideally a major lender or policy bank (e.g. a Chinese policy or state-owned commercial bank).
  • Standby letter of credit: some structures use an SBLC instead of a guarantee.
  • Acceptable issuer: the owner and its lender must approve the issuing bank's credit standing — this is a key negotiation point.

Demand vs conditional — the clause that decides whether it pays

TypeHow it paysRisk
Demand guaranteePayable on a simple demand and statement, without proof of defaultStrongest for the owner; the bank pays first, disputes later.
Conditional guaranteePayable only on proof of the yard's default (arbitration award or judgment)Weaker — the owner must first prove default, often after long arbitration.

Key point: push for a demand (on-first-written-demand) guarantee governed by a predictable regime such as the URDG 758 rules. A conditional guarantee can leave you financing the yard's default through years of arbitration before you see a cent.

Governing law and the autonomy principle

  • Autonomy: the guarantee is independent of the underlying shipbuilding contract — the bank pays on the guarantee's own terms.
  • Governing law: commonly English law or the issuing bank's home law; the URDG 758 rules are standard.
  • Jurisdiction: often arbitration or the courts of a neutral forum, aligned with the finance documents.

Key terms to scrutinise

  • Amount and partial calls: does it cover all instalments, and can you call for part of the amount?
  • Expiry: it must extend beyond the anticipated delivery date plus the warranty/cancellation window.
  • Reduction provisions: many guarantees reduce as instalments are repaid or milestones pass — check the reduction mechanics.
  • Assignability: the guarantee should be assignable to your lender as part of the security package.
  • Call events: tie the call to contract cancellation, yard insolvency and delivery default.

How we help

  1. Structure the guarantee: demand basis, URDG 758, acceptable issuer and governing law.
  2. Negotiate the terms: amount, expiry, reductions, assignability and call events.
  3. Align with financing: integrate the guarantee into the lender's security package.
  4. Enforce calls: pursue payment and defend against wrongful-call injunctions if the yard or bank resists.