Choosing the contract form

Two forms dominate newbuild orders at Chinese yards, alongside yard-drafted terms:

  • BIMCO NEWBUILDCON: the international standard, heavily buyer-friendly, and widely accepted by top Chinese yards.
  • CMAC standard form: the China Maritime Arbitration Commission's standard shipbuilding contract, common among domestic and some cross-border orders.
  • Yard-drafted terms: many yards push their own form — usually buyer-unfriendly on delay, warranty and supervision.

Which form you start from matters, but the amendments matter more. The same yard standard can be negotiated into a balanced or a one-sided deal depending on clause-level drafting.

Price and payment milestones

Newbuild prices are usually paid in instalments tied to construction milestones, not at delivery. A typical structure:

InstalmentMilestoneTypical share
1Contract signing10%
2Steel cutting10%
3Keel laying10%
4Launching10%
5Delivery60%

Because 40% or more is paid before the vessel exists, the refund guarantee covering those instalments is the single most important protection in the deal.

Delivery and delay

  • Delivery date: fixed, with a permitted-delay window (force majeure and permitted delays) before liquidated damages kick in.
  • Liquidated damages: a daily rate for late delivery, capped at a percentage of the price.
  • Cancellation: the buyer may cancel after excessive delay (typically 180 days) and call the refund guarantee.
  • Specification: the vessel's technical description and approval procedure — disputes here are the most common.

Key risk: the specification and "approved drawings" clause governs almost everything technical. Ambiguity there becomes a price or delay dispute later. Precision at the specification stage is the cheapest insurance in a newbuild.

Supervision, supplies and warranty

  • Buyer's supervision: the right to appoint surveyors and attend trials and inspections.
  • Buyer's supplies: owner-furnished equipment and its delivery timing and risk.
  • Warranty: the defect-warranty period after delivery (commonly 12 months) and the guarantee repair scheme.
  • Law and arbitration: choice of law and forum — a clause-level decision with outsized consequences.

How we help

  1. Form selection: start from NEWBUILDCON or CMAC, not a yard draft.
  2. Clause negotiation: price, milestones, delay, cancellation, warranty and supervision terms.
  3. Specification drafting: lock down the technical description and approval procedure.
  4. Dispute-proofing: align the law and arbitration clause with your financing and enforcement strategy.