Choosing the contract form
Two forms dominate newbuild orders at Chinese yards, alongside yard-drafted terms:
- BIMCO NEWBUILDCON: the international standard, heavily buyer-friendly, and widely accepted by top Chinese yards.
- CMAC standard form: the China Maritime Arbitration Commission's standard shipbuilding contract, common among domestic and some cross-border orders.
- Yard-drafted terms: many yards push their own form — usually buyer-unfriendly on delay, warranty and supervision.
Which form you start from matters, but the amendments matter more. The same yard standard can be negotiated into a balanced or a one-sided deal depending on clause-level drafting.
Price and payment milestones
Newbuild prices are usually paid in instalments tied to construction milestones, not at delivery. A typical structure:
| Instalment | Milestone | Typical share |
|---|---|---|
| 1 | Contract signing | 10% |
| 2 | Steel cutting | 10% |
| 3 | Keel laying | 10% |
| 4 | Launching | 10% |
| 5 | Delivery | 60% |
Because 40% or more is paid before the vessel exists, the refund guarantee covering those instalments is the single most important protection in the deal.
Delivery and delay
- Delivery date: fixed, with a permitted-delay window (force majeure and permitted delays) before liquidated damages kick in.
- Liquidated damages: a daily rate for late delivery, capped at a percentage of the price.
- Cancellation: the buyer may cancel after excessive delay (typically 180 days) and call the refund guarantee.
- Specification: the vessel's technical description and approval procedure — disputes here are the most common.
Key risk: the specification and "approved drawings" clause governs almost everything technical. Ambiguity there becomes a price or delay dispute later. Precision at the specification stage is the cheapest insurance in a newbuild.
Supervision, supplies and warranty
- Buyer's supervision: the right to appoint surveyors and attend trials and inspections.
- Buyer's supplies: owner-furnished equipment and its delivery timing and risk.
- Warranty: the defect-warranty period after delivery (commonly 12 months) and the guarantee repair scheme.
- Law and arbitration: choice of law and forum — a clause-level decision with outsized consequences.
How we help
- Form selection: start from NEWBUILDCON or CMAC, not a yard draft.
- Clause negotiation: price, milestones, delay, cancellation, warranty and supervision terms.
- Specification drafting: lock down the technical description and approval procedure.
- Dispute-proofing: align the law and arbitration clause with your financing and enforcement strategy.